DEME Offshore’s cable installation vessel ‘Living Stone’, featuring its unique dual-lane cable system, will be deployed to lay inter-array cables on Dogger Bank C
Dogger Bank Wind Farm has signed an EPCI contract with DEME Offshore for the inter-array cables at the 1.2GW Dogger Bank C phase of what will be the world’s largest offshore wind farm. Today’s announcement follows the earlier award of the Dogger bank A and B inter-array cable contract to DEME in early 2021.
The scope of this new EPCI agreement includes the engineering, procurement, construction and installation of the subsea cables for the 1.2 GW phase of the wind farm. DEME Offshore will supply, install and protect approximately 250 km of 66 kV inter-array cables and all related accessories.
Production of the cables for Dogger Bank C is set to start in 2023. The cables will be installed in 2025 and DEME will once again be deploying its DP3 cable installation vessel ‘Living Stone’. Living Stone boasts an inhouse designed dual-lane system, consisting of two cable highways – this allows cable laying using one lane whilst the next cable can be simultaneously prepared and have the cable protection system (CPS) installed on the other lane. As previously demonstrated, this significantly reduces the time needed for preparing the cables, minimises manual handling, increases the vessel’s workability and ultimately, improves production rates.
Dogger Bank Wind Farm is located more than 130km off the North East coast of England and is currently being delivered by joint venture partners SSE Renewables, Equinor and Eni. The wind farm is being developed in three 1.2 GW phases, A, B and C. Upon completion, Dogger Bank will be the world’s largest offshore wind farm and will generate energy to power up to 6 million homes every year.
"After securing the Dogger Bank A and B inter-array cable contract earlier this year, we are proud to now also confirm the inter-array cable contract for the Dogger Bank C wind farm. This contract not only demonstrates the unrivalled cable-laying capabilities by our DEME Offshore team, it is also further testament to the stellar reputation of our DP3 cable installation vessel ‘Living Stone’."
Bart De Poorter General Manager of DEME Offshore
"We are delighted to award the contract for the supply, installation and protection of the inter-array cables at Dogger Bank C wind farm to DEME Offshore, extending our existing relationship with DEME on phases A and B to the third phase of this project. This will ensure continued synergies across the construction activities of the offshore wind farm, including the deployment of DEME’s state-of-the-art cable installation vessel ‘Living Stone’ which will install the almost 250 km of 66 kV inter-array cables required to connect Dogger Bank C’s offshore turbines."
Simon Bailey SSE Renewables’ Commercial Director for Dogger Bank Wind Farm
Dogger Bank A and B is a joint venture between SSE Renewables (40%), Equinor (40%) and Eni (20%). On 2 November 2021 SSE and Equinor announced the sell down of a combined 20% share in Dogger Bank C to Eni (10% each). The transaction is expected to close in Q1 2022, subject to regulatory and lenders approvals and customary purchase price adjustments. Eni will enter the asset effective from completion of the sell down transaction. Once the transaction is complete, the new overall shareholding in Dogger Bank C will be SSE Renewables (40%), Equinor (40%) and Eni (20%).